Types of works: turnkey with design
Location: Izhevsk
Construction area: 200 sq.m
Construction time: July 2014-December 2014
The value of investments: 15 000 000 RUB

Works:
– removal of existing floors
– foundation work for control measuring machine
– foundation work for pillars
– polymer floor covering
– metal frame mounting
– installation of crane equipment (crane beam Q=5tons)
– wall assembly and sandwich panel covering
– assembling of roll shutter gates and doors
– installation of “Armstrong” suspended ceiling system
– piping and setting of compressed air 6.3 bar
– sanitary piping with one network incut for condensate drain from supply unit
– electrics: lighting, socket installation, crane-beam connection, gate connection, connection of the air handling unit
– automation: installation and commissioning
– ventilation: installation of air handling ductwork, installation of air handling units to maintain the temperature in the room